What is the delivery time for tire-mounted gantry cranes?
The delivery time for tire-mounted gantry cranes (RTGs) varies greatly depending on tonnage, level of automation, power supply type, and batch size.

I. Typical Delivery Times
1. Standard RTG (41–60 tons, stacking 5 to 6 units, non-automated)
Single unit/Small batch (1–3 units): 75–90 days (from contract signing to delivery)
Batch (5–10 units): 90–120 days
Turnkey (including on-site installation and commissioning): Add 15–30 days
2. Automated/Intelligent RTG (including remote control and automatic stacking)
Single unit: 120–150 days
Batch (5 units and above): 150–180 days
3. Heavy-duty/Customized (70 tons and above, hybrid/pure electric, large span)
Single unit: 120–180 days
Complex customized (explosion-proof, ultra-high, AGV-based): 180–240 days II. Key Factors Affecting Delivery Time
Tonnage and Specifications
41–60 tons (mainstream): Shortest delivery time
70 tons and above, large span (>26m), ultra-high lifting: More complex structure and drive system, longer delivery time
Automation and Electronic Control
Manual/Semi-automatic: Shortest delivery time
Fully automatic/Remote/Intelligent scheduling: High proportion of software and system integration, significantly longer delivery time
Power Supply
Diesel/Mainland Electricity: Relatively short delivery time
Pure Electric/Lithium Battery/Hybrid: High degree of battery and electronic control customization, increased delivery time by 20–30 days
Batch Production and Scheduling
Single Unit: Fastest
5 units or more: Requires batch production, longer total delivery time
Peak Season (Q1, Q4): Delivery time increased by 15–30 days
Delivery Scope
Factory delivery only: Shortest delivery time
Including transportation, installation, commissioning, certification, and training: Overall delivery time increased by 30–60 days
III. How to Shorten Delivery Time
Prioritize 41–60 ton standard stacker models (5 or 6 models)
Clearly define non-automatic/ Basic automation requirements reduce later changes. Bulk orders can have production schedules locked in 3-6 months in advance.